How to plan a product launch

A twelve-week plan for launching a software product: five teams, fifteen activities, a go/no-go review, three milestones and a mandatory offsite. The three views show the same plan and stay in step: drag an activity in one and the others follow.

Open in Tidigar: Product launch – Plan by team

Gantt chart: will every team be ready in time

The plan grouped by team, with activity names on the left; each milestone sits in the row of the work it waits for.

The go/no-go decision is a two-day review, not just a date. It waits for the fixes, the campaign, the pipeline and support readiness; Release rollout and Press briefings wait for it, and Go/no-go sits beside it. Give the review one more day and the milestone, the launch work and Launch day all move one work day later. The yellow band is the offsite: the plan counts work days and treats it as time off, so the release and the launch page lose four days there. Hold the review with this view on screen.

Kanban board: what is happening now

Rows show teams and columns show completion.

Open in Tidigar: Product launch – Board by team

The brief and the interviews are done; engineering and marketing are working. Each card shows its dates: drag Sales training a week later in the Gantt chart and its card here, and the cards of the work after it, show the new dates. In a weekly launch meeting each team speaks to its own row, and a row full of In progress is a team doing too much at once.

Flowchart: what decides launch day

Lanes show the teams and each arrow is a dependency.

Open in Tidigar: Product launch – Dependencies

Diamonds mark where work splits into chains that all run; Go/no-go review is one because both the rollout and the briefings follow it, and the shape does not mean a yes-or-no branch. Two chains have no gap between their steps and set launch day: the marketing chain from the interviews through positioning, launch page and campaign, and the engineering chain through the release, the beta and the fixes. Warm up the pipeline and Support readiness end two work days before the review, and the sales chain, including Sales training, could finish that much later. Dragging an activity keeps those gaps and moves everything after it.

Make it yours

  1. Open in Tidigar under any view gives you your own copy. It is free, needs no account and stays on your device.
  2. Rename or remove the activities that differ in your launch.
  3. Drag Launch brief to your real start week; the work after it follows.
  4. Update completion on the board as work moves.

Frequently asked questions

How long is a product launch plan? Eight to twelve weeks is common for a software release with a campaign; a small update may need four, a new market or hardware more.

Which teams belong in it? Every team that must be ready on launch day: usually product, engineering, marketing, sales and support.

What is a go/no-go review? A short meeting before launch where every team confirms it is ready. If one is not, the date moves before it is announced.