How to plan a conference
A fourteen-week plan for a one-day customer conference: four teams, thirteen activities, three milestones and an early-bird window, shown in three views that stay in step. The conference day is fixed; the preparation before it can move.
Gantt chart: the work that leads up to a fixed day
The timeline groups the work by team and plans it backwards from the event date, which is set with the venue and cannot move.
Conference day is a fixed milestone, drawn as an outline diamond. Registration opens waits for the Event website and Line-up announced for the Agenda. Follow-up and survey waits for the conference day, so it moves only when the event does. The green band is the early-bird window, from 15 February to 14 March.
Kanban board: what each team is doing now
The board puts each activity in a column by progress, with a row for each team.
Early in the plan, the budget, venue and sponsor packages are done, while the call for speakers, website and sponsor sales are under way. Sponsor sales run for seven weeks and feed the booths and the rehearsal; a card that stays in In progress that long deserves a weekly look.
Checklist: what is due when
The same activities as a list, with the due date, the team and progress.
Choose the End column heading to sort by due date. Try a slip in the timeline: drag Sell sponsorships one week later. Signage and booths and the Technical rehearsal move by the same week, so the rehearsal's due date reads 21 April, six days after the conference. Conference day stays on 15 April and Tidigar shows no warning, because a fixed milestone is an anchor, not a deadline.
Make it yours
- Choose Open in Tidigar under any view to get your own copy. It is free, needs no account and stays on your device.
- Open Conference day and set your event date; the follow-up moves with it.
- Drag Goals and budget to your real start; the preparation after it follows. Check that Technical rehearsal ends before the conference day, and if work slips past it, shorten the booth work, end sales earlier or add help.
- Rename the teams to match your organization.
- To keep an updating view on the event team's office screen or in their calendar, keep your copy in a Tidigar Business team, where screens and calendar feeds are included. Choose Share → Screens… for the saved Checklist view, make a screen and follow Screen links. Anyone with the screen link can view it without an account.
- On the screen's page, choose Calendar subscription → Copy calendar link so the team can subscribe without a Tidigar account. Technical rehearsal appears on its planned day and Conference day as a one-day milestone; the early-bird band is not a calendar event. Anyone with the address can read the view, and calendar apps may take hours or longer to update, so tell the team about urgent changes near the event.
Frequently asked questions
How far ahead should you plan a conference? Three to four months for a one-day event with a few hundred guests; six months or more when the venue is in high demand.
What should be booked first? The venue and date. Speakers, sponsors and marketing all depend on them.
What if preparation runs past the event date? The date stays where it is. Use the timeline or the checklist to find the late work, then shorten it or cut scope; moving the event is a decision for the venue and the guests.
Related
- Two kinds of milestone: a fixed date that work waits for.
- Moving activities and dependencies: why a slip carries on through the chain.
- Board and List: group cards by team and stage, sort the list.
- Timeline views: group rows by team, show periods.
- Screen links and calendar feeds: an updating screen or calendar feed (Tidigar Business).